Name of Work: Package D: All Civil and Architectural work for Power House, TG Foundation including deck, BFP Foundations, Transformer Foundations ( GT, ST & Aux.Transformer Foundations ), and Transformer Yard all civil works and DG Building etc. excluding Power House Structural Fabrication and erection for Unit# 3 & 4 AT 4X270 MW Thermal Power Station, Manuguru, Distt-Khammam, Telangana.

Brief Description of Work: AP Genco is setting up 4 x 270 MW Thermal Power Plant, where M/s BHEL was awarded main contract. M/s BHEL have awarded the above work to M/s BJCL, a Delhi base company from whom we have taken up the works on back to back basis.

Client : M/s. BJCL

Value of Work : Rs.35,50,00,000 (Rupees Thirty Five  Crore  Fifty Lacks only)

Date of Work Order  : 05.12.2015

Contract Period : 18 Months

Contractual date of Completion  : 04.06.2017

Reasons for delay : We have mobilised the site to start all the activities, after about a month of works,  due to an NGT order on the main contractor the works have been stopped. Now the NGT have cleared the project and awaiting MOEF clearance for final go ahead which is expected by 15th Feb’2017.

Name of Work: Package 3 : Construction of Road Bed, Major and Minor Bridges, track Linking ( Excluding Supply of rails and PSC Line Sleepers), General Electrical, Tractional and Signal & Tele Communication works (Outdoor) and Construction of Staff Quarters in connection with Doubling With Railway Electrification of Bhimavaram – Nidadavole Section (Incl. Bhimavaram Jn, Bhimavaram Town, Nidadavole Jn) From KM 105.00 to Km 154.75 on Vijayawada division of South Central Railway vide IFB No. RVNL/SC/BZA-GDV-BVRM-NDD-NS-MTM/168, dated 27-05-2015 vide LOA No. RVNL/SC/BZA-GDV-BVRM-NDD-NS-MTM/168/Package-3 dt:02-06-2016

 Brief Description of Work: M/S RVNL have been entrusted the work of doubling the railway line between Bhimavaram – Nidadavole by Indian Railways, where M/s SRI SCL Infratech Limited was awarded main contract. In turn M/s SCL have awarded us a portion of the above stretch viz., Tanuku – Attili section and from Km 123.000 to Km 124.000 on Item Rate basis.

Client : M/s. SRI SCL INFRATECH LIMITED

Value of Work : Rs.14,00,00,000 (Rupees Fourteen  Crore  only)

Date of Work Order  : 31.12.2016

Contract Period : 18 Months

Contractual date of Completion  : 30.06.2018.

Name of Work: Erection, testing, commissioning, and all related civil works of(i)220 KV, 2-Phase, DC/SC Line from the 220 KV SS Nansuralla to the proposed RTSS Pendekallu (12 Kms), (ii) 220 KV 2 nd Circuit Stringing from the existing 220 KV Dhone SS to the Nansuralla SS (28Kms), (iii).1 No of 220 KV Bay at 220 KV Dhone SS,(iv) 2 nos of 220 KV Bays at Nansuralla, (v)1 no. Of 220 KV Bay at RTSS Pendekallu, all in Kurnool District, Andhra Pradesh State

 Brief Description of Work: M/S Transmission Corporation of Andhra Pradeshhave awarded the work to M/s .R.K. Electric Automation Limited.  In turn M/s R.K. Electric Automation  have awarded us the Schedule “B” of the above works.

Client : M/s. R.K. Electric Automation Limited , Hyderabad

Value of Work : INR. 3,22,11,968/- (Indian Rupees Three Crores Twenty Two Lakhs Eleven Thousand Nine Hundred Sixty Eight Only).

Date of Work Order  : 20.04.2017

Contractual date of Completion : 19.12.2017

Contract Period : 8 Months